Full internal refurbishment of Dubai apartments, planned around the two things that actually decide what is possible: the slab and the building's rules.

What We Do

The Slab Decides What Is Possible

Apartment renovation in Dubai is constrained in ways villa work is not, and almost all of it comes back to one thing: you cannot cut the slab.

That single fact determines whether a bathroom can move, whether a kitchen island can have a sink, and whether an open-plan layout is achievable or merely a nice drawing. Waste needs a consistent fall to reach the existing stack. Where the fall is not available, the floor has to be built up or a step formed — which is often perfectly acceptable, but only if it is designed in rather than discovered halfway through.

The second constraint is the building itself. Towers and managed developments impose approval processes, restricted working hours, lift and loading bay bookings, refundable deposits and waste removal routes. These are programme drivers, not paperwork.

We survey the existing drainage and confirm the building's requirements before proposing a layout, so what you are shown is buildable and the programme reflects reality.

Request a Fixed-Price Quotation
Scope of Works

What an Apartment Refurbishment Covers

Everything achievable within the constraints of a concrete frame and a managed building.

Drainage Survey

Establishing stack positions, available falls and existing routes before any layout is drawn. This determines whether wet areas can move and by how much.

Layout & Partitions

Removing and forming non-structural partitions, opening up living space, and reconfiguring entrance halls and storage within the frame.

Kitchens

Replacement and reconfiguration, including island units where the extract route and drainage allow. The extract run to an external wall is the usual limiting factor.

Bathrooms

Complete refits with full tanking and a twenty-four hour flood test — non-negotiable in an apartment, where a leak becomes your neighbour's ceiling and your insurance claim.

Finishes & Joinery

Flooring, fitted wardrobes, feature walls, doors, decorative plaster and paint, plus lighting design and smart controls.

Building Compliance

NOC applications to building management, contractor and labour passes, insurance documentation, deposit handling, and scheduling around permitted working hours.

Budgeting

Apartment Renovation Costs in Dubai

Indicative figures for a like-for-like layout, excluding structural or drainage relocation.

Indicative Dubai apartment renovation ranges, August 2026. Excludes VAT, building deposits and authority fees.
ScopeWhat it includesIndicative range
Cosmetic refreshPaint, flooring, light fittings, sanitaryware swap.AED 60k – 130k
Kitchen onlyReplacement kitchen, worktops, appliances, local services rework.AED 45k – 120k
Full refit, 1–2 bedStrip-out, kitchen, bathrooms, flooring, joinery, lighting.AED 180k – 400k
Full refit, 3–4 bedAs above at a higher specification, with layout reconfiguration.AED 400k – 800k

Two costs are routinely underestimated in apartment projects. The first is access: material deliveries and waste removal via a service lift on a booking system, often outside business hours, is slower and more expensive than it sounds. The second is protection — corridors, lift lobbies and common areas all have to be sheeted and reinstated to the building's satisfaction.

Both appear as preliminaries in our bill of quantities rather than surfacing later as extras.

Approvals & Programme

What Apartment Approvals Actually Involve

An apartment renovation needs two permissions and sometimes three. Your building's owners association issues the fit-out NOC, which governs access, service lift bookings, working hours, contractor registration and the refundable deposit. Where the works touch structure, drainage or the approved layout, an authority permit is required on top.

The third applies where the building sits in a district with its own authority. DIFC is a separate jurisdiction, JLT answers to DMCC, Dubai Silicon Oasis to DSOA and the Barsha Heights districts to DDA. A contractor who assumes Dubai Municipality in one of those has gone to the wrong body, and submissions are rejected rather than forwarded.

Allow two to five weeks for the building NOC, and three to six where an authority permit runs alongside it. The limiting factor is almost always an incomplete document set rather than the assessment itself.

Indicative programme for a full apartment renovation
StageDuration
Survey, drawings and measured bill of quantities2 – 3 weeks
Building fit-out NOC and any authority permit2 – 5 weeks
Strip-out, services and first fix3 – 6 weeks
Second fix, joinery and finishes4 – 7 weeks
Testing, snagging and handover1 – 2 weeks
What Differs

Why an Apartment Is Not a Small Villa

Three things change the job. Access, because every delivery, every skip load and every length of joinery moves through a booked service lift within permitted hours, and joinery that will not fit the lift has to be designed in sections before it is made.

Drainage, because moving a wet area means new runs crossing a slab above another owner, working on the falls available within a floor build-up that is often only sixty millimetres. Many buildings prohibit it outright, and that constraint decides the layout rather than the drawing does.

And cooling, because in most towers you do not own the plant. District cooling means the chillers are the building's and what you own is the fan coil unit, the valves and the condensate drainage — which is where comfort problems almost always sit, and why replacing a thermostat rarely changes anything.

How We Price

How We Price an Apartment Renovation

Benstead is run by a quantity surveyor. We do not price an apartment by walking through it and naming a figure — we measure it, and you receive a bill of quantities with every element listed, quantified and rated.

That makes two quotations comparable line by line instead of leaving you to guess why one number is larger, and it gives an agreed rate for anything that changes mid-project rather than a negotiation while the apartment is in pieces.

For an indicative range in about a minute, use the Dubai renovation cost calculator. Before signing anything, why renovation quotes vary and red flags in a renovation quote are worth ten minutes.

Questions

Apartment Renovation FAQs

Can I move the bathroom or kitchen in an apartment?

Sometimes, and it is the single most constrained decision in an apartment project. Waste needs a consistent fall to reach the existing stack, and the slab cannot be cut.

Relocation therefore usually means building up the floor or forming a step. That is often perfectly acceptable — but only if it is designed in. We survey the drainage before proposing any layout.

What approvals does an apartment renovation need?

Building management or the owners association will require drawings, method statements, contractor insurance, a refundable deposit and passes for every operative.

Where you are altering layouts, drainage or anything structural, a Dubai Municipality or relevant free zone authority permit is required on top. We handle both submissions.

How disruptive is it for neighbours?

Manageable when it is planned for. Buildings restrict noisy works to set hours, typically mid-morning to late afternoon on weekdays only.

We programme percussive work into those windows, seal the entrance to control dust, and clean common areas daily. In our experience complaints come from contractors ignoring building rules far more often than from the works themselves.

Who approves an apartment renovation in Dubai?

Your building's owners association issues the fit-out NOC covering access, lift bookings, working hours and the deposit. Where the works touch structure, drainage or the approved layout you also need an authority permit — Dubai Municipality in most districts, but DIFC, DMCC in JLT, DSOA in Silicon Oasis and DDA in Barsha Heights each have their own.

Can I move a bathroom in an apartment?

Often not, and it depends on the building. Moving a wet area means drainage crossing a slab above another owner, working on the falls available within a build-up that is frequently only sixty millimetres. Many buildings prohibit it in their fit-out rules. Where it is permitted it needs a drainage design, the building's consent and an authority permit.

Why is my apartment never cool enough?

In most towers the cooling is a district system, so there is no condenser of your own. The usual causes are a fouled or undersized fan coil unit, a valve that is not modulating, or ductwork never balanced after handover. Replacing the thermostat or the unit alone frequently changes nothing.

How long does an apartment renovation take?

Around twelve to eighteen weeks on site for a full renovation, plus two to five weeks beforehand for the building NOC and any authority permit. Service lift availability and restricted working hours are what stretch an apartment programme rather than the work itself.

What about the service lift?

It is usually the binding constraint on the programme. Every delivery, skip movement and joinery section is a booked slot, and in a large tower those slots are contested. We size joinery to the lift at design stage and sequence the bookings, because a two-week installation becomes four if that is left to chance.

Apartment Renovation Costs

What should an apartment renovation cost?

A full apartment renovation in Dubai commonly falls between AED 180,000 and AED 800,000 depending on size and specification, with tower access, service lift bookings and restricted working hours adding to both the price and the programme. For an indicative range against your own floor area and scope, use the Dubai renovation cost calculator.